Possible bug in new UI - Cockpit - Tasks

  • July 11, 2016
  • 4 replies
  • 39 views

ben_daniels
In my cockpit view I'm noticing that a lot of the tasks are not updating properly in the view. For example a CTA will have 2/5 tasks completed however in the list view it only shows 1/5. This is happening for multiple CTAs.

4 replies

manu_mittal
Forum|alt.badge.img+3
  • Gainsight Employee ⭐️
  • July 11, 2016
Thanks for sharing, Ben. I was able to reproduce this issue in your org (via LMA). We'll look into the root cause and connect back with you soon.

ben_daniels
  • Author
  • Contributor ⭐️⭐️⭐️
  • July 11, 2016
Thank you!!!

ben_daniels
  • Author
  • Contributor ⭐️⭐️⭐️
  • July 13, 2016
One more thing I'd like to note because I suspect they are related - we don't have access to view any playbooks at all. When we click on Playbooks it just brings up a blank page. 

ben_daniels
  • Author
  • Contributor ⭐️⭐️⭐️
  • July 13, 2016
Disregard this piece, it looks like it was a permissions issue.