Skip to main content
Question

Hi is there a way to change the activity type for to-dos created in timeline?

  • May 16, 2018
  • 1 reply
  • 50 views

nancy_burdzel
As an example, our internal teams are looking to modify the activity type within timeline, as generally these "to-dos" or tasks tie back to work that is already categorized, like an escalation.  By having consistency across these to-do's back to the broader activity type, we could potentially have the opportunity to better quantify the work being completed by CSMs.

1 reply

seth
Forum|alt.badge.img+7
  • Gainsight Employee ⭐️⭐️⭐️
  • 550 replies
  • May 16, 2018
The Types of Activities in Timeline is customizable:

     



Documentation here: 
https://support.gainsight.com/Product_Documentation/Customers_and_Relationships/Admin_Configuration/...

However, after an activity is logged, the type cannot be changed. You can vote for that feature here: https://community.gainsight.com/gainsight/topics/option-to-change-type-in-timeline

Or, you could create a custom field for Activity "sub-type" or "purpose", which would be editable after-the-fact.

Reply